Machinery maintenance logs: what PUWER expects you to keep
Updated
The repair fixes the machine; the record is what an inspector, insurer or buyer sees. Here is what the regulations say, and what a usable log looks like.
What the regulations say
Production machinery is work equipment under the Provision and Use of Work Equipment Regulations 1998. Two regulations matter here.
Regulation 5 (Maintenance) requires work equipment to be maintained in an efficient state, in efficient working order and in good repair. Where machinery has a maintenance log, the log must be kept up to date.
Regulation 6 (Inspection) requires inspection where safety depends on how the equipment was installed, or where conditions cause deterioration. The result is recorded and kept until the next inspection.
Read that carefully: PUWER does not oblige every machine to have a maintenance log. It obliges you to keep one up to date where the machine has one, and inspection records where regulation 6 applies. If safe operation depends on maintenance, you want the log anyway.
What a usable log contains
- Asset identity
- Machine, make, model, serial number and location. If your maintenance system cannot tell two identical machines apart, the log is not evidence of anything.
- Date and who did the work
- Named engineer or contractor, with their company. An unsigned entry is hard to rely on later.
- What was done
- Planned service, inspection or breakdown repair, described in enough detail that someone else can tell what was and was not touched.
- Parts fitted
- Part numbers and whether new, refurbished or manufactured. This is the record that saves you a week of sourcing next time.
- Readings taken
- Vibration, temperature, pressures, alignment, insulation resistance, whatever the discipline uses. Trends are worth more than single readings.
- Work identified but not done
- The most valuable field in the whole log, and the one most often left blank. It becomes your planned work list and your evidence that a known issue was managed rather than ignored.
- Next action and date
- What is due next and when, so the log drives the schedule instead of describing the past.
Getting the record out of your contractor
- Ask for the report format before you place the order. A photograph of a handwritten worksheet is not a maintenance record you can search.
- Ask for readings, not just outcomes. "Bearing replaced" tells you nothing about why it failed.
- Ask for parts detail with numbers. It is the difference between a two-hour repeat repair and a two-week one.
- Ask for the work-identified list separately, so it can go straight onto your planned maintenance plan.
- File it against the asset, not against the invoice. Finance filing and engineering filing are not the same job.
Why it changes what repairs cost you
A machine with a real history gets diagnosed faster, because the engineer can see what has already been changed and what keeps failing. A machine with no history is charged for the time it takes to work that out from scratch, every time. The log is the cheapest thing on this site.